- This topic has 3 replies, 2 voices, and was last updated 3 years ago by .
Viewing 4 posts - 1 through 4 (of 4 total)
Viewing 4 posts - 1 through 4 (of 4 total)
- The topic ‘Bpp revision kit qn 37’ is closed to new replies.
OpenTuition recommends the new interactive BPP books for March 2025 exams.
Get your discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Bpp revision kit qn 37
How to find the bottleneck resources for this Qn I didn’t understand the solution they gave …how did they get 12 units??
In washing they are capable of making (1,200 x 60) / 6 = 12,000 units per hour.
In filling they could make (700 x 60) / 3 = 14,000 units
In capping they could make (250 x 60) / 1.5 = 10,000 units
In Labelling they could make (450 x 60) / 2 = 13,500 units
The smallest is 10,000 units and it is therefore capping that is the bottleneck resource.
I don’t know why BPP has messed around with 12 units. It is not necessary and wastes time.
Thanks
You are welcome 🙂