Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › BPP Revision Kit Part C OTQ Bank Question 112
- This topic has 6 replies, 3 voices, and was last updated 4 years ago by John Moffat.
- AuthorPosts
- July 15, 2020 at 8:33 am #576854
Sir
I didn’t understand why products 1000 units each of X, Y and Z needs to be purchased externally.
8000 units is the maximum capacity of the company and when 4000 units of W can be bought externally, only 1000 units of Z needs to be bought along with it.
The rest of the units 2000 of X+ 3000 of Y + 3000 of Z will make up to the internal capacity of 8000 units right?September 2, 2020 at 8:36 pm #583174i have this same confusion. did you get answer?
September 3, 2020 at 9:39 am #583214Q112 in the current edition of the BPP Revision Kit has nothing about X, Y and Z. It is about price elasticity of demand.
September 4, 2020 at 10:56 am #583395thanks. i am using one valid upto june 2020.
September 4, 2020 at 4:28 pm #583469I am using the one valid up to June 2021. However I have found the question – it is number 122 in the current edition.
If they buy 4,000 units of W externally they will save $1,000. If in addition they bought only 1,000 units of Z externally then they would have an extra cost for Z of 2,000 (the variable cost) because since they would still be making some Z’s in-house they would not be saving the fixed costs. So doing that would lose them a net $1,000.
If however the buy all 4,000 units of Z externally (and produce none themselves) then they would save the fixed costs and the extra cost would only be 1,000. So buying 4,000 W and 4,000 Z externally would have no net effect the costs. Any other way would increase the costs overall.
October 20, 2020 at 1:25 pm #590790Thank you Sir. I have cleared PM and I’m extremely grateful to you for your guidance and notes.
October 21, 2020 at 8:07 am #590926That is great news. Many congratulations 🙂
- AuthorPosts
- The topic ‘BPP Revision Kit Part C OTQ Bank Question 112’ is closed to new replies.