Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › BPP mock 2 question 4
- This topic has 7 replies, 2 voices, and was last updated 10 years ago by
John Moffat.
- AuthorPosts
- November 29, 2014 at 12:44 pm #214338
Sir I would like to know the got 7,800 litres in calculating operational labor efficiency variance. BPP Mock Exam 2, Section B, question 4.
even if we use standard cost, without units produced we an find it.November 29, 2014 at 1:28 pm #214390I do not have the BPP Mock Exam – sorry. You will have to ask BPP.
November 29, 2014 at 1:36 pm #214399the standard direct labor for 100 liters is 8 hours at $24 per hour
actual hours, 640 hours at a cost of $16500.
It has now been realized that a new wage is $26 per hour and had been agree with workers.
calculate the operational labour efficiency variance
Sir I would like to know the got 7,800 litres in calculating operational labor efficiency variance. BPP Mock Exam 2, Section B, question 4.
even if we use standard cost, without units produced we an find it.November 29, 2014 at 1:42 pm #214404In the question you have typed, there is not enough information!
November 29, 2014 at 2:20 pm #214418is all I have. the original question is for labor rate planning and operational variance. im ok with that. but my problem is about labor efficiency operational variance. there is not information for that but . the answer should have been nil as there is not revised hours, but it is not. sir with just these information, the labor operational variance shouldn’t be nil.
I can’t ask bpp as my only tutor is you!!!!
November 29, 2014 at 4:31 pm #214455It seems to me as though BPP have left out part of the question.
I am really sorry that I cannot help.However, since you have paid BPP for the mock exam, they really should be able to explain to you what they have done.
November 29, 2014 at 4:35 pm #214457sir I didn’t pay for any exam, it is included in the revision kit.
November 29, 2014 at 5:16 pm #214474Well, the same applies! As you have typed it then there is not enough information. Since you have paid for the revision kit then you really should complain to BPP.
I cannot help when there is not enough information given in the question 🙂