If the shadow price for Month 2 is $125 per labour hour, which of the following statements is/are correct? (a) The production manager would be willing to pay existing staff a maximum overtime premium of $125 per hour for the next 2,000 hours (b) The production manager would be willing to pay a maximum of $170 per hour for an additional 2,000 hours of temporary staff time ? 1 only ? 2 only ? Both 1 and 2 ? Neither 1 nor 2
I dont understand why is it additional 2000 hours?