In this Question I can’t understand the logic why labour for extra shift is calculated in this way:
$110000+($110000*0.15*1.50)?
Because it means an extra shift.
This would mean an extra 110,000 anyway.
But in addition they will have to pay an extra 50% and (because it is a variable cost and sales will increase) and extra 15% as well.
Thank you Mr. Moffat for your expert and soon respond!