• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

BFG Limited Question ( Learning Curve )

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › BFG Limited Question ( Learning Curve )

  • This topic has 6 replies, 3 voices, and was last updated 1 year ago by LMR1006.
Viewing 7 posts - 1 through 7 (of 7 total)
  • Author
    Posts
  • November 16, 2023 at 4:57 pm #694972
    nanisaid98
    Participant
    • Topics: 13
    • Replies: 17
    • ☆

    BFG Limited is investigating the financial viability of a new product the S-pro. The S-pro is a short-life product for which
    a market has been identified at an agreed design specification. The product will only have a life of 12 months.
    The following estimated information is available in respect of S-pro:
    1. Sales should be 120,000 in the year in batches of 100 units. An average selling price of $1,050 per batch of 100
    units is expected. All sales are for cash.
    2. An 80% learning curve will apply for the first 700 batches after which a steady state production time will apply,
    with the labour time per batch after the first 700 batches being equal to the time for the 700th batch. The cost of
    the first batch was measured at $2,500. This was for 500 hours at $5 per hour.
    3. Variable overhead is estimated at $2 per labour hour.
    4. Direct material will be $500 per batch of S-pro for the first 200 batches produced. The second 200 batches will
    cost 90% of the cost per batch of the first 200 batches. All batches from then on will cost 90% of the batch cost
    for each of the second 200 batches. All purchases are made for cash
    5. S-pro will require additional space to be rented. These directly attributable fixed costs will be $15,000 per
    month.
    A target net cash flow of $130,000 is required in order for this project to be acceptable.
    Note: The learning curve formula is given on the formulae sheet. At the learning rate of 0.8 (80%), the learning
    factor (b) is equal to -0.3219.

    this is the answer :

    For first seven hundred batches y = axb
    y = 2,500 x 700 –0.3219
    y = $303.461045

    Why they use 2500 for first total hour? Should it be 500 hours?

    November 16, 2023 at 5:56 pm #694975
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1487
    • ☆☆☆☆☆

    This was for 500 hours at $5 per hour.

    It doesn’t matter when you * $5 but you have to.

    November 17, 2023 at 3:06 pm #695016
    nanisaid98
    Participant
    • Topics: 13
    • Replies: 17
    • ☆

    i still dont understand? Why they used $2500 but not 500 hours?

    This is my working

    Y = (500) (700) ^ -0.3219

    I dont get the same answers like the book

    November 17, 2023 at 4:02 pm #695018
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1487
    • ☆☆☆☆☆

    The question asks you to:

    Prepare detailed calculations to show whether product S-pro will provide the target net cash flow.
    Therefore you have to work out the labour cost as well as materials etc

    Therefore what you have done is right BUT you need to multiply by labour cost $5
    You have to value it

    So its got to be * $5

    y = axb
    y = 500 x5 x 700^ –0.3219
    y = $303.461045
    Total cost for first 700 batches = $303.461045 x 700 = $212,423

    All batches after the first 700 will have the same cost as the 700th batch.
    To calculate the cost of the 700th batch we need to take the cost of 699 batches from the cost of 700 batches.
    For 699 batches
    y = a x b
    y = 500 x 5 x 699 ^–0.3219
    y = $303.600726
    Total cost for first 699 batches = $303.600726 x 699 = $212,217

    Cost of 700th batch is $212,423 – $212,217 = $206

    Total cost for the 12 months of production $212,423 + ($206 x 500) = $315,423

    February 3, 2024 at 8:53 am #699662
    CERTIFIED7784
    Participant
    • Topics: 0
    • Replies: 2
    • ☆

    This is clear now Thanks

    February 3, 2024 at 8:55 am #699663
    CERTIFIED7784
    Participant
    • Topics: 0
    • Replies: 2
    • ☆

    Can you also explain how they calculated for variable overheads

    February 3, 2024 at 1:21 pm #699675
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1487
    • ☆☆☆☆☆

    Total labour cost ($212,423 + $103,000) = $315,423

    Variable overhead = 126,169

    Variable overhead is $2 per labour hour, or 40% of the direct labour cost which is 2/5
    $2 var o/h compared to $5 labour costs

    $315,423 * $2 / $5

  • Author
    Posts
Viewing 7 posts - 1 through 7 (of 7 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Ken Garrett on Project management – ACCA Strategic Business Leader (SBL)
  • Kim Smith on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)
  • Farhaan on Project management – ACCA Strategic Business Leader (SBL)
  • Ken Garrett on Professionalism, ethical codes and the public interest – ACCA Strategic Business Leader (SBL)
  • thienan0110 on Interest rate risk management (1) Part 5 – ACCA (AFM) lectures

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in