Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › APV ( adjusted present value) question strayer
- This topic has 1 reply, 2 voices, and was last updated 10 years ago by John Moffat.
- AuthorPosts
- October 11, 2014 at 7:56 am #204129
hi sir
can you please help me outi am trying to understand the logic behind the APV
step 1: is to calculate the base case NPV
we assume that the $25 m will be raised through 100% equity finance
but when it says to calculate the issue costs it says in the question that issue cost is 4% of the equity finance
it only took 10m x 4% = $ 0.40m
so we are assuming that the issue cost is included in the equity finance of $10m
so we need to remove the issue cost in the $10m and the issue cost in the $5m debt finance because the issue cost will change if we borrow more equity finance
why was it not removed
if the issue cost was not included you would have calculated it differently
ie: 10m x 100/96 = 10.4166mbut clearly in the $10m it was included
so that means the total amount to be raised via equity finance in the base case NPV cannot be $25m
because the issue costs of both the equity and debt finance is included
can you please help me out. maybe i am wrongly understanding something
thank you very much
October 11, 2014 at 10:06 am #204144The answer has assumed that only $10M in total was raised from equity, and that the issue costs were paid out of internal funds, so that there remained $10 from the issue for investment in the project.
If you had assumed as you wish to (that the equity raised was actually a little more than $10M in order to cover the issue costs) then you would still have got full marks (even though obviously the final answer would have been slightly different).
- AuthorPosts
- You must be logged in to reply to this topic.