Skip to content

Ask the Tutor ACCA PM

Advance Variances

FFathmath7y ago
QUESTION As a result of the results in January to March, Kamal Co reconsidered its approach to budgeting and adopted a form of rolling budgeting, starting in April for the next twelve months. The budgeted figures for the remainder of the year before the rolling budget was introduced were as follows: $ April-June 550,000 July-September 560,000 October-December 575,000 Kamal Co amended the budget so that budgeted sales for April-June were 20% higher than in the original budget, and then increased by 5% in July-September and October-December. It did not subsequently amend the budget for July-September. Actual sales for July-September were $610,000. Calculate the difference in the total sales operational variance, using the original budgeted and revised (rolling) budgeting figures. ANSWER Variance calculated using original budget = $610,000 – $560,000 = $50,000 F Revised budget = $550,000 × 120% × 105% = $693,000 Variance calculated using revised budget = $610,000 – $693,000 = $83,000 A Difference = $50,000 + $83,000 = $133,000 My question is why do they minus $560000 from $610000 if the question asks us to find operational variance?
John MoffatJohn MoffatTutor7y ago#1
It is because the question is not asking for the operational variance, it is asking for the difference in the operational variances. If the sales had not been revised, then the operational variance would have been the difference between actual and original budget, which is 50,000 F After they have been revised, the difference between actual and revised is 83,000 A So the difference between the two is 133,000.
FFathmath7y ago#2
Thank you so much
John MoffatJohn MoffatTutor7y ago#3
You are welcome :-)
Topic lockedNew replies are closed.