• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

Adjusted Present Value – Subsidised loans

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › Adjusted Present Value – Subsidised loans

  • This topic has 8 replies, 2 voices, and was last updated 4 years ago by kumkumsri.
Viewing 9 posts - 1 through 9 (of 9 total)
  • Author
    Posts
  • April 28, 2021 at 7:38 pm #619107
    kumkumsri
    Member
    • Topics: 1
    • Replies: 5
    • ☆

    Hi John. This is a question in BPP 2019 edition
    Gordonbear is about to start a project requiring $6 million of initial investment. The company normally borrows at 10% but a government loan will be available to finance the entire project at 8%. Tax is payable at 30% with no delay. The project is scheduled to last for four years.
    Calculate the effect on the APV calculation if Gordonbear finances the project by means of the government loan.
    How would this be solved?

    April 29, 2021 at 7:41 am #619145
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54659
    • ☆☆☆☆☆

    The effect on the base case NPV is to add the tax benefit on the interest payments (30% x 8% per year, discounted for 4 years) and also to add the benefit of the subsidy of 2% per year for 4 years.

    I explain how to do this in my free lectures on APV.

    (and does your book not have an answer and explanation?)

    May 1, 2021 at 6:51 pm #619388
    kumkumsri
    Member
    • Topics: 1
    • Replies: 5
    • ☆

    So this is the solution given in the text book. As you can see the interest rate used for calculating the amount of interest is 10% and not 8%. Im arriving at $722,760 but the answer is $951,000.

    Solution
    (a) Step 2 of the APV would be as follows.
    We assume that the loan is for the duration of the project (four years) only. Annual interest = $6 million x 10%
    = $600,000
    Tax relief = $600,000 x 0.3
    = $180,000
    This needs to be discounted over Years 1 to 4 at the normal cost of debt of 10%. NPV tax relief = $180,000 x Discount factor Years 1 to 4
    = $180,000 x 3.170
    = $570,600
    However, we also need to take into account the benefits of being able to pay a lower interest
    rate.
    Benefits = $6 million x (10% – 8%) x 10% discount factor Years 1 to 4
    = $6 million x 2% ? 3.170
    = $380,400
    Total effect = $570,600 + $380,400 = $951,000.

    May 2, 2021 at 8:20 am #619403
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54659
    • ☆☆☆☆☆

    The total effect is 836,880. You can get this 2 ways.

    One way is as the answer in the book has done it, although there is a mistake:

    The tax saving on interest at 10% = 570,600 (as per the workings you have shown).
    The subsidy benefit is 6M x (10 – 8)% x 0.7 x 3.170 = 266,280 (the 0.7 is because the tax saving has been calculate as though the interest was 10%, the subsidy benefit gains us 2% but loses the tax saving on the 2% so is only 0.7 times the saving.
    Total of the two is 570,600 + 266,280 = $836,880

    The other way is as follows:

    Tax saving on interest at 8% = 6M x 8% x 0.3 x 3.170 = 456,480
    Subsidy saving: 6M x (10-8)% x 3.170 = 380,400
    Total of the two is 456,480 + 380,400 = $836,880

    Either way is acceptable. The examiner sometimes does it the first way in his answers and sometimes does it the second way 🙂

    May 2, 2021 at 5:14 pm #619453
    kumkumsri
    Member
    • Topics: 1
    • Replies: 5
    • ☆

    This is another worked example I came across.
    Here they have considered the tax relief lost while they have calculated the PV of the interest payment at the subsidised rate. I’m a bit confused regarding the tax relief calculation for the PV of the subsidised loan.

    A plc requires $1 million in debt finance for 5 years.
    It has borrowed $700,000 in the form of 10% bonds redeemable in
    5 years and the remainder under a government subsidised loan scheme at 6%. The tax rate is 30%. Assume that tax is delayed one year.

    (a) PV of the tax shields
    Although the cheap loan has a cost of 6% it has the same risk as a normal loan, therefore the appropriate discount rate is 10% pa.
    Annual tax relief = Total loan × interest rate × tax rate
    700,000 × 0.10 × .30 = 21,000 x 3.791 x 0.909 = 72,366
    300,000 × 0.06 × .30 =72,366 x 3.791 x 0.909 = 18,609
    Annuity factor for 5 years @10% Discount factor for 1 year @10% PV of the tax shield

    (b) PV of the cheap loan
    Annual amount
    300,000 × (10% – 6%) = 12,000 × .30 = 12,000 x 3.791 = 45,492
    Annuity factor for 5 years Present value factor – PV of the cheap loan
    Tax relief lost = 3,600 x 3.791 x 0.909 = (12,406)

    Total = 124,061

    May 2, 2021 at 5:56 pm #619461
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54659
    • ☆☆☆☆☆

    That is doing exactly as I explained in my previous reply to you.

    The only difference is that the tax is delayed for a year and so the PV of the tax relief needs discounting for the extra year.

    May 2, 2021 at 6:10 pm #619466
    kumkumsri
    Member
    • Topics: 1
    • Replies: 5
    • ☆

    I get that the tax is delayed for a year but we are calculating the interest amount at the subsidised rate and wouldn’t that mean while calculating the PV of the subsidised loan the tax relief part is not included because we are including only the opportunity benefit of availing the subsidised loan?

    May 3, 2021 at 7:53 am #619499
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54659
    • ☆☆☆☆☆

    That is correct. It does seem that there is a mistake in the answer and that although the tax benefit calculation is correct, the benefit of the subsidy should be calculated on the full 4% and not on 4% after tax.

    May 3, 2021 at 8:23 am #619506
    kumkumsri
    Member
    • Topics: 1
    • Replies: 5
    • ☆

    Okay. Thank you for clearing my doubts John. 🙂

  • Author
    Posts
Viewing 9 posts - 1 through 9 (of 9 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • barbjohn on Equity Law, Ratio Decidendi – ACCA LW Global
  • Kakui on Equity Law, Ratio Decidendi – ACCA LW Global
  • Nicholas1239798 on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)
  • Starmoon123 on Strategy formulation (Part 2) – ACCA (AFM) lectures
  • nosiphoceliwedlamini@gmail.com on Revenue – Example 5 (profitable contracts) – ACCA Financial Reporting (FR)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in