• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

March 2026 ACCA Exams

Comments & Instant poll

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for June 2026 exams.
Get your discount code >>

ACCA Practice Mock MA Exam 2

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › ACCA Practice Mock MA Exam 2

  • This topic has 5 replies, 2 voices, and was last updated 3 years ago by John Moffat.
Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • September 18, 2022 at 2:16 pm #666670
    chacki
    Participant
    • Topics: 3
    • Replies: 3
    • ☆

    Hi,

    Please can you help with the below question:

    One material is used in the manufacture of product X. The total cost of the material (purchased and used) in a period was $4,000. In the period, the direct material price and usage variances were $200 adverse and $300 favourable respectively and 1,000 units were manufactured.

    What is the standard direct material cost per unit for product X?

    $3.90
    $4.30
    $3.80
    $4.10

    The answer is $4.10. The working out was: (4000-200+100)/1000

    Can you explain why they do 4000 – 200 + 100. My understanding was 4000 was the actual cost they need to work out the standard budgetted cost so should do 4000 + 200 – 100. Please can you me understand this?

    Thanks,

    September 18, 2022 at 4:20 pm #666685
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54835
    • ☆☆☆☆☆

    There is obviously a typing mistake in the workings because (4,000 – 200 + 100)/1,000 does not equal $4.10 !!

    The answer is $4.10 and the correct workings are as you have written towards the end.

    September 18, 2022 at 4:36 pm #666688
    chacki
    Participant
    • Topics: 3
    • Replies: 3
    • ☆

    Sorry there was a typo. The solution said (4000-200+300)/1000. But I don’t understand why.

    I thought actual cost was 4000 so we had to work backwards using the variance to calculate the standard direct material cost per unit i.e. (4000+200-300)/1000?

    September 19, 2022 at 7:36 am #666703
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54835
    • ☆☆☆☆☆

    If the figures are as you have now typed then the answer should indeed be as you have written.

    I can only assume that there is a typing mistake in the question.

    Where did you find the question?

    September 19, 2022 at 9:18 am #666709
    chacki
    Participant
    • Topics: 3
    • Replies: 3
    • ☆

    This question is from the ACCA Practice Test Papers

    Sorry, so if I understand correctly the correct working out is: (4000+200-300)/1000. So the answer is 3.9. Is that correct?

    September 19, 2022 at 6:47 pm #666736
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54835
    • ☆☆☆☆☆

    Sorry, I have been confusing you (although you have been confusing me by typing something wrongly initially 🙂 )

    Given that the actual cost was $4,000 and the price variance was $200 adverse, then the actual cost must have been 200 more than the standard cost, So the standard cost would be 4,000 – 200.

    Similarly, since the usage variance was $300 favourable, the actual cost must be 300 less than the standard cost, so the standard cost must be $300 more than the actual cost.

    So the printed answer is in fact correct. (4,000 – 200 + 300) / 1,000

  • Author
    Posts
Viewing 6 posts - 1 through 6 (of 6 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Kaplan ACCA Free Trial

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE Exams – Instant Poll

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Pompaciadem on Risk and Uncertainty – Decision Trees Part 2 – ACCA Performance Management (PM)
  • Kim Smith on Auditors’ Rights, Appointment, Removal, Resignation and Regulation – ACCA Audit and Assurance (AA)
  • Breadtoast67 on Strategy formulation (Part 2) – ACCA (AFM) lectures
  • adatya on Auditors’ Rights, Appointment, Removal, Resignation and Regulation – ACCA Audit and Assurance (AA)
  • John Moffat on Inventory Control (part 1) The EOQ Formula – ACCA Management Accounting (MA)

Copyright © 2026 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in