• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

ACCA BPP Section B T Co – Practice and Revision Kit

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › ACCA BPP Section B T Co – Practice and Revision Kit

  • This topic has 1 reply, 2 voices, and was last updated 2 years ago by John Moffat.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • January 29, 2023 at 11:15 am #677570
    chacki
    Participant
    • Topics: 3
    • Replies: 3
    • ☆

    Hi,

    Can you please help me understand the below question?

    the installation is expected to take one week to complete and would require three engineers, each of whom is paid a monthly salary of $4000.The engineers have just had their annually renewable contract renewed with T co. One of three engineers has spare capacity to complete the work but the other two would have to be moved from contract x in order to complete this one. Contract X generates a contribution of 200$ per engineer per week. There are no engineers available to continue with Contract X if these two engineers are taken off the job.it would mean that T co would miss its contractual completion deadline on Contract X by one week. As a result, T co would have to pay a one-off penalty of 500$.Since there is no other work scheduled for their engineers in one week’s time, it will not be a problem for them to complete contract x at this point.

    The question asks to: What figure should be included in the relevant cost statement for engineers’ cost?

    The answer in the textbook is $500.

    My question is why isn’t the VC and the opportunity cost of contribution foregone not included aswell?

    January 29, 2023 at 3:52 pm #677592
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    They will not be losing any contribution from Contract X because they will still be completing it.
    The only cost involved will be the penalty of $500 because they will be one week later in completing it.

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Gowri7 on Relevant cash flows for DCF Working capital (examples 2 and 3) – ACCA Financial Management (FM)
  • Govere on The use of ratios and comparisons in auditing
  • John Moffat on Relevant cash flows for DCF Working capital (examples 2 and 3) – ACCA Financial Management (FM)
  • Gowri7 on Relevant cash flows for DCF Working capital (examples 2 and 3) – ACCA Financial Management (FM)
  • Ken Garrett on The nature and structure of organisations – ACCA Paper BT

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in