- This topic has 1 reply, 2 voices, and was last updated 8 years ago by .
Viewing 2 posts - 1 through 2 (of 2 total)
Viewing 2 posts - 1 through 2 (of 2 total)
- You must be logged in to reply to this topic.
Interactive BPP books for June 2026 exams, recommended by OpenTuition.
Get discount code >>
Forums › FIA Forums › Absorbing costs
A manufacturer absorbs production overheads into the cost of jobs as a percentage of actual direct labour cost. Two
jobs were worked on during a period:
Job 1 ($) Job 2 ($)
Opening work-in-progress 5,269 –
Direct materials in the period 10,726 4,652
Direct labour in the period 4,360 2,940
Production overheads of $9,855 were incurred in the period. Job 2 was completed in the period.
What is the value of work in progress at the end of the period?
A $20,972
B $24,941
C $26,241
D $20,355
You must have an answer in the same book that you found the question. Kindly refer to the answer and tell us what is it in the answer that you don’t understand.
