June 2025 ACCA Exam Results

Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for June 2025 exams.
Get your discount code >>

97 Bath co

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › 97 Bath co

  • This topic has 5 replies, 2 voices, and was last updated 9 years ago by John Moffat.
Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • May 18, 2016 at 8:54 pm #315701
    Igrar
    Participant
    • Topics: 28
    • Replies: 24
    • ☆☆

    Im part b , in external material cost for division A, the answer includes 20000×200. I understand that 20000 is the remaining number of units after B’s outside sales and this number it sells to division A , but what is the 200$ cost there?where did they got it?

    May 19, 2016 at 7:50 am #315740
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54702
    • ☆☆☆☆☆

    The question says that Division A pays $200 for fittings from Division B for each bath.

    May 25, 2016 at 3:15 pm #317071
    Igrar
    Participant
    • Topics: 28
    • Replies: 24
    • ☆☆

    Fittings from division B ——–75$
    But not 200$. 200$ is the other materials from external suppliers. Isnt it?

    May 25, 2016 at 3:52 pm #317082
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54702
    • ☆☆☆☆☆

    The current costs of A for every bath are the amount to A (75) plus the amount for external fittings (200) plus the labour (which is show separately in the statement.

    For part (b) of the question, it is assumed that the transfer price changes to $65 – the price that A can buy from outside (although as the answers says, it would be the same end result for any transfer price between 20 and 65).

    In that case, the costs of each bath will be the amount to A or to external (65) plus the external fittings (200) (plus again the labour)

    Division B has maximum production of 200,000 units and the external demand is 180,000.
    So the sales to A will be the remaining 20,000.

    A has demand for 80,000. So 20,000 will be bought from A and 60,000 will be bought externally.

    The 60,000 they buy externally will cost 265 payable externally.
    The 20,000 they buy from A will also cost 265, but 200 will be paid externally and 65 will be paid to A (and the external and internal amounts are shown as separate lines in the profit statements).
    (So the total costs of A = 80,000 x $265 = 21,200,000, of which 19,900,000 is paid externally and 1,300,000 is paid internally)

    May 25, 2016 at 4:04 pm #317086
    Igrar
    Participant
    • Topics: 28
    • Replies: 24
    • ☆☆

    Thank you Sir for explanation!

    May 25, 2016 at 5:39 pm #317094
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54702
    • ☆☆☆☆☆

    You are very welcome 🙂

  • Author
    Posts
Viewing 6 posts - 1 through 6 (of 6 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • verweijlisa on Financial performance – Example 2 – ACCA Financial Reporting (FR)
  • John Moffat on Linear Programming – Spare capacity and Shadow prices – ACCA Performance Management (PM)
  • John Moffat on The Statement of Financial Position and Income Statement (part d)
  • Salexy on Linear Programming – Spare capacity and Shadow prices – ACCA Performance Management (PM)
  • omerbasheer on The Statement of Financial Position and Income Statement (part d)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in