2017 sep/dec question 1Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA APM Exams › 2017 sep/dec question 1This topic has 2 replies, 2 voices, and was last updated 5 years ago by teeboyz.Viewing 3 posts - 1 through 3 (of 3 total)AuthorPosts February 26, 2019 at 3:35 pm #506617 teeboyzMemberTopics: 19Replies: 52☆☆hello john/ken sircan i ask why is the development cost for the answer is different from the question, question says development and design costs are 120M, but model answer written 100M,did i miss something?thanks February 27, 2019 at 9:18 am #506672 Ken GarrettKeymasterTopics: 10Replies: 10544☆☆☆☆☆The development cost of 120m is spread over 1200 engines to give 100,000 per engine. February 27, 2019 at 11:47 am #506693 teeboyzMemberTopics: 19Replies: 52☆☆thank you so muchAuthorPostsViewing 3 posts - 1 through 3 (of 3 total)The topic ‘2017 sep/dec question 1’ is closed to new replies.