Paper F2 This is not a quote its actually a question can anyone answer Please help with workings for this question
A company operates a job costing system. Job number 1203 requires $300 of direct materials and $400 of direct labour. Direct labour is paid at the rate of $8 per hour. Production overheads are absorbed at a rate of $26 per direct labour hour and non-production overheads are absorbed at a rate of 120% of prime cost. What is the total cost of job number 1203. I have the answer i just don’t understand how the got it please help