• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

teddylove

Profile picture of teddylove
Active 4 years ago
  • Topics: 10
  • Replies: 17
  • ☆
  • Profile
  • Forums
  • Topics Started
  • Replies Created
  • Engagements

Forum Replies Created

Viewing 17 posts - 1 through 17 (of 17 total)
  • Author
    Posts
  • July 20, 2020 at 3:58 am #577418
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    Sir John, I have studied and would like to double confirm:

    A) When we have Product A (one type of Product), and we would like to (outsource or in-house manufacture), this is how we calculate relevant cost

    Outsourcing cost (Total cost of Purchasing/ also known as Variable cost of buying)
    vs.
    In-house Manufacturing cost (total variable cost and avoidable cost, for example, DM,DL, Variable MOH, Specific Fixed Cost, Incremental cost, avoidable cost).

    B) When we have two different products which are currently in-house manufacturing

    Variable Cost, Incremental Cost, Avoidable cost (Minimum cost) of Product A
    vs
    Minimum Cost of Product B

    In this case, unavoidable cost are not included in the relevant cost, as they are the same in both situation as both are still in house manufacturing

    The lower cost will be viable for decision making

    C) When we have one product which are in-house manufacturing with limiting factor (Machine Hour, Labour Hour, Materials), this is how we calculate relevant cost

    Limiting Factor A (Machine Hour)
    only the variable cost (DM, DL, Variable MOH)
    vs
    Limiting Factor B (Labor Hour)
    only the variable cost (DM, DL, Variable MOH)

    in this case, the specific/ incremental fixed cost are not included, as they are the same in both situation

    Relevant cost are difficult to understand, but it is easier if we understand the concept and the decision of the company. A confirmation from you would mean so much to me, appreciate Ask my tutor forum so much !

    July 19, 2020 at 8:43 am #577348
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    Sir, it is said that Zero Based Budgeting (ZBB) eliminates budgetary slack (which are discretionary costs and support activities) in the fixed budget. Can we incorporate budgetary slack to certain extent in ZBB?

    Or is it only those selective costs like Variable Costs (costs with clear input and output relationship) only can accept budgetary slack to a certain extent?

    July 18, 2020 at 3:35 pm #577323
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    Sir, I had understood that Part A of the question (means the Robber Co is currently manufacturing the production, hence, those avoidable/ specific fixed cost are included)

    Wheres, the Part B says that Robber Co (wishes to increase), means it haven’t incur, so specific/ avoidable cost are excluded (Am I right in my first understanding Sir)

    Sir, besides,

    For Note 3, the statement had stated clearly that the heat and power/ fixed cost,
    it is incurred irrespective of whether the components are manufactured in house or not.

    For Note 4, the fixed cost haven’t incur, so not included in the variable cost

    For Note 5 of Specific Fixed Cost,
    Attributable fixed costs are fixed costs that only occur is the particular process or production takes place.

    In conclusion, Total fixed cost irrespective of incur or not, it is irrelevant to the production unit, because regardless of the total units of 1 unit or 10 unit, it would still be the same,

    If the question did not give assumption, can I exclude fixed cost from the VC of internal manufacturing vs VC of outsourcing (if the manufacturing haven’t happen)?

    July 18, 2020 at 3:51 am #577253
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    Tq Sir John, but you havent answer my question of this 🙁

    sir, for calculating standard profit

    we only calculating
    std SP- All the production cost,

    but we dont take into account the non production cost

    am i right sir?

    July 17, 2020 at 10:58 am #577073
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    sir, for calculating standard profit

    we only calculating
    std SP- All the production cost,

    but we dont take into account the non production cost

    am i right sir?

    July 9, 2020 at 6:40 pm #576448
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    Thank you Sir John. I finally understood relevant costing based on your assistance in Ask My Tutor Forum

    July 9, 2020 at 6:37 pm #576447
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    Understood sir. thanks for clarification

    July 9, 2020 at 1:51 pm #576422
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    the installation is expected to take one week to complete and would require three engineers each of the following is paid monthly salary of $4000. the engineers just had their annually renewable contract renewed with T Co. One of the three engineers has spare capacity to complete the work, but other two have to be moved from Contract X in order to complete this one. Contract X generates a contribution generates the contribution of $5 per engineer hour.there are no other engineers to continue the Contract X if these two companies are taken off the job it would mean that T Co would miss it contractual deadline of Contract X by one week. As a result T Co would have to pay a one-off penalty of $5000. Since there is no other work for scheduled for their engineers in one week’s time it will not be a problem for them to complete Contract X at this point

    i am calculating the lost contribution from contract X
    sorry sir, but the question does not state the “engineer hours”
    i think i had made a mistake by comparing it ,
    if the question didnt mention engineering hour
    how do we compare both lost contibution and penalty to find the cheaper cost then?

    July 9, 2020 at 9:52 am #576411
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    A special job for a customer require 8 tonnes of a material M. The company no longer uses this material regularly although it holds 3 tonnes in inventory. These originally costs $44 per tonne, and could be resold to a supplier for $35 per tonne. Alternatively these materials could be used to complete another job instead of using other materials that would cost $126 to purchase. The current price of Material M is $50 per tonne.

    In comparing in the first question and second question (current post)

    I would like to confirm my understanding.

    for the first question, company has either choice of buying “Swipe 2” and modify “Swipe 1”, and (Swipe 1 is not currently using in the production process. in this statement, we would like to find the cheapest (cost)

    for the second question, company is currently using material M, and we would like to compute what the company would do with the material if they did not do the special job, finding the better total (savings).

    For relevant cost, we would like find the
    1) cheaper cost
    2) higher savings.

    I would like double confirm my understanding, and thank you Sir John

    July 8, 2020 at 5:14 pm #576357
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    sir for relevant cost, we choose which one is cheaper is it?

    between lost contribution ($8 hours X $5 per hour X 2 engineer X 7 days)= $560
    and penalty =$500,

    so the cheaper one is included as relevant cost, as its cheaper?
    bcos based on my understanding, company would like to incur a cheaper cost for their decision making

    July 8, 2020 at 4:57 pm #576355
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    Dear sir, for flexed budget, i would like to double confirm

    for service industry in order to derive at Std cost, we would flex with ‘actual sales unit’

    for production industry, we would flex with ‘actual production unit’

    July 8, 2020 at 1:01 pm #576328
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    Thank you SIr John, you make my learning easier! Bless you!

    July 8, 2020 at 12:50 pm #576326
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    Hi SIr John,
    in batches in ABC,
    based on my understanding,

    for example,

    each batch inside consists of production units,

    the overhead costs are absorbed by production units inside the “batch”,

    a past year question has change the question by increasing the amount of batch from 400 to 500,

    so we need to determine the new amount of production unit inside the batch to determine the accurate overhead cost allocation right?

    July 6, 2020 at 5:09 pm #576142
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    Thank you Sir John, I finally understood this topic well. Wish you well.

    July 6, 2020 at 5:05 pm #576141
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    unincorporated entities consist of (individuals) include
    1) sole proprietor forming his/her own business
    2) partnership

    right sir? and the treatment of it are looking on individual basis

    whereas incorporate entities are solely business, and the tax treatment of it are looking at the company basis.

    thank you sir

    July 6, 2020 at 10:59 am #576103
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    to acquire the lowest possible minimum WACC

    July 6, 2020 at 10:58 am #576102
    mysteryteddylove
    Member
    • Topics: 10
    • Replies: 17
    • ☆

    Based on the lecture I had just watch, is the optimal capital structure is
    60 (equity) : 40 (debt) right?
    Thank you Sir John

  • Author
    Posts
Viewing 17 posts - 1 through 17 (of 17 total)

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • hhys on PM Chapter 4 Questions Environmental Management Accounting
  • singhjyoti on Conceptual Framework – ACCA SBR lecture
  • John Moffat on Time Series Analysis – ACCA Management Accounting (MA)
  • azubair on Time Series Analysis – ACCA Management Accounting (MA)
  • Gowri7 on Relevant cash flows for DCF Working capital (examples 2 and 3) – ACCA Financial Management (FM)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in