Able Ltd is considering a new project for which the following information is available: Initial cost – $300,000 Expected lite – 5 years Estimated scrap value – $20,000 Addition revenue from the project – $120,000 per year Incremental costs of the project – $30,000 per yadi Cost of capital – 10%
Calculate the Accounting Rate of Return of the project (to the nearest %).