Answer is $55100
Work in progress is Total Direct labor cost that is $55400. We have to exclude overtime work from it .. that is 30 hours are overtime and $10 is basic rate.
30 × 10 = 300
Total direct labor excluding overtime will be = $ 55400 – 300
$ 55100