Forum Replies Created
- AuthorPosts
- March 12, 2024 at 12:10 pm #702917
I am still confuse due to this example :
That If we Agree NCA Register to Physical Asset present at floor is existence.
And If we Agree Physical Present Asset on Floor to NCA Register is Completeness.Same Should be the case with Shares Register/Shares Annual Report while agreeing with Share certificates issued.
Like If we Agree Shares Register/Shares Annual Report to Shares Certificate issued it should be existence,
And If we Agree Shares Certificate to Shares Register/Shares Annual Report then it should be completeness, As Per my Understanding but you told the opposite of this, kindly elaborate it, where I am getting wrong by the why ?
As it came in my exam and I did it according to my understanding.March 11, 2024 at 7:56 am #702725I am unable to see the answer relevant to my question as in this link nothing mentioned regarding shares capital or share register ?
Please Help Me Out.
January 30, 2024 at 2:37 am #699301Thanks for your response,
But I still have a question that Revenue lost is opportunity cost and we can write in explanation that it is opportunity cost. but how it can be incremental revenue ? Because there is nothing that is incremental to revenue.And How cost saving can be incremental cost ?
Because cost will not incur if we shut down a division, so how can it be called as incremental cost ?June 24, 2022 at 8:33 am #659206Hi SIR,
I had passed my exam today by getting good marks, thanks for your consistent help during the preparation for my exam, Thank you very muchA question came in my exam as follows :
Which of the following would be problems when measuring the performance of a non-profit seeking publicly funded hospital that does not charge for it’s services at the point of consumption ?1) Multiple conflicting objectives
2) Measuring the value of outputs1) 2 only
2) 1 only
3) Both 1 and 2
4) Neither 1 nor 2Please confirm me the answer for this one, I will be very thankful to you.
June 21, 2022 at 5:48 am #659047Sir I listened to your lecture TWICE, But unfortunately my concept is not enough clear and I am not able to get the correct answer for above question.
Kindly Let me know the correct answer for above question with some short reason so it may clear my concept and please let me know that work study department is internal or external source ?Many thanks
June 17, 2022 at 10:32 am #658920Yes your Answer is 100% correct but follow this method.
(2000*0.5) + (1000*0.65) + (240 * 0.75) = 1830
Standard rate is $10 * 3240 units = 32400
Add = 34230If you have any other query do let me ask .
June 16, 2022 at 2:30 pm #658871When we have to find probability we must deduct the amount which we find from table from 0.5.
It is mandatory and remember this for your whole life.
I don’t know why we do this but to find probability it is necessary.June 16, 2022 at 1:57 pm #658868Let me make you understand
z=47-37/4 = 2.5
okay then you have to see 2.5 in row and 00 column you will find 0.4938
Than from 0.5 you have to subtract this amount
I mean 0.5-0.4938 and then multiply by 100 to get answer in percentage’
you will definitely find 0.62 %
June 16, 2022 at 1:35 pm #658865You re Welcome.
June 16, 2022 at 1:26 pm #658862Hi there I can tell you the answer for this It is quite easy.
Let me make you understand.
In this question it is asking about standard deviation okay
So first of all you had exactly done right till this step that you found the answer 0.43 or 0.4300
After this you have to Find this value or nearest to this value in the Distribution table ( not at the side of column or row ) but in the middle of the table, exact value is not available (0.4300) so you have to take this value 0.4306 instead of 0.4300.
Now see the Row and column in which this value is present I mean 0.4306, You will find 1.4 in row and 0.08 in column which means 1.48 and this is required and after that you will get your standard deviation easily.
That is Standard Deviation 6.76.
If you have any question let me ask.June 13, 2022 at 8:27 am #658606I did not found the answer there.
This is about relevant costing.
The first question is that the revenue is $50 per hour and 30$ Variable cost per hour and 10$ Fixed cost per hour.
So what will the opportunity cost for those hours in which the taxi will be in maintenance ? PROFIT $10 OR CONTRIBUTION $20 ?And second one this theory question .
WHICH OF THE FOLLOWING ARE ADVANTAGES OF REMEDIAL MAINTENANCE ?
1) THE ANNUAL COST OF MAINTENANCE CAN BE ACCURATELY FORECAST
2) THE SERVICE PROVIDED TO CUSTOMERS WILL BE MORE RELIABLEOPTIONS:
BOTH 1 AND 2
1 ONLY
2 ONLY
NEITHER 1 OR 2 - AuthorPosts