Understood. Thanks a lot for helping me to see this through from a different perspective. I’m just wondering if each unit of product A uses 1 meter of sheet metal as the calculation used to determine the pressing time needed for Product A to satisfy maximum demand for 300 000 units is (0.5 * 300 000)= 150 000 pressing hours for Product A whereby this is derived from the multiplication of the time taken per unit, which is 0.5 hrs per meter per unit by the maximum demand of 300000 units for product A.
(As this is an adapted question, I have difficulty with this part here. I am able to calculate the TPAR from the earlier part of this question.)