Forum Replies Created
- AuthorPosts
- June 16, 2016 at 9:05 pm #323228
@killip123 said:
You did the same as I did in the exam… the $6.5m NPV was for the whole project life, so didn’t need to times that by the 7 years, just needed to do the square root of 7 x 1.3^2 and divide $6.5m by the answer to give the number of standard deviations (approx 3.44) 6.5/3.44= 1.89 in the table – which is 0.4706. Add 50% to give 97.06% confident cashflows won’t be negative.I’m kicking myself now as it was 4 easy marks wasted.
I did it differently:
VaR = N (confidence level) x s x square root T
for confidence level 95% the number of standard deviations is 1.645 (from the tables)
s – annual standard deviation of project returns
T – number of years
So VaR = 1.645 x 1.3m x Sq.root 7 = $5.66m, which is potential monetary loss and is below the project’s NPV of 6.5m
So at the given level of confidence the project is worthwhile.June 16, 2016 at 8:54 pm #323226Q1: doing APV I got negative base case NPV and even adding tax shield and subsidy effect the total APV was also negative. Seems incorrect. Did anybody get the same result?
January 24, 2016 at 7:44 pm #297736Passed 68%. This was 3rd attempt. I would not say that Dec.2015 exam was difficult comparing to previous sessions. I expected that there will be foreign currency consolidation and IFRS 15 question. And they were in the exam!
August 1, 2015 at 6:52 am #264001Passed 58% at second attempt. Thanks God!
- AuthorPosts