Interactive BPP books for September 2026 exams, recommended by OpenTuition.
Get discount code >>
Plz help me Sir. My F2 exam is in 2 days. 🙁
Although I can see the answer, I don’t understand the way they calculate.
I want to know how to calculate to get the answer $0.06 for staff cost per invoice.
For invoices per hour, I want to know the reason why 2500 is divided by 7×5.
For cost of idle time, I don’t understand why $32 is added by $2.2. I don’t even know how and why $2.2 appears.
Please explain it to me, Sir.
I want to know the definition of absolute numbers, Sir.
So why do we need to calculate the ARR first in this question? Can’t we calculate the IRR directly.
I want to know how ARR can be used to estimate the discount rate of the project.
This is the quiestion:
Find the IRR of the project given below and state whether the project should be accepted if the
company requires a minimum return of 17%.
Time $
0 Investment (4,000)
1 Receipts 1,200
2 ” 1,410
3 ” 1,875
4 ” 1,150
Could u plz give me the link to ur lecture videos?
I don’t understand yet. How do u count those 2 months? Plz explain it to me in detail.