Yes Performance Measurement Was Such A Disaster :<
Absorption & Abc Requirements Are CALCULATE FULL PRODUCTION COST PER UNIT
Mine Was Same Ahmed 🙂
i Think
24x+10y<1800000
10x+30y<1680000
42x+20y<720000
X<70000
Y<85000
X,Y>0
Contribution=30x+40y
Essem: In Linear Programming Fixed Cost is i Think 640,000 or 64000 Given in The Question. But It Was PER MONTH & We Were Working On For The QUARTER So i MULTIPLIED The Fixed Cost By 3.
Aleksandr & Essem:
For Product X ABC Is Jus a Little Bit Higher (Both Are 90 Something)
For Product Y ABC is 83 Something & 92 Something in Absorption
For Product Z ABC is Higher
In Linear Programming My Result is X=20,000 & Y=66,000
But Most Of The Students Saying X=55,000 & Y=66,000
So Whats The Correct Answer Guys?