Forum Replies Created
Viewing 4 posts - 1 through 4 (of 4 total)
- AuthorPosts
- July 5, 2020 at 1:59 pm #576056
@johnmoffat said:
The actual cost = 38/0.95 = 40.
Material is 10, so labour is 30.
Labour is paid 8 per hour, so it must be 30/8 = 3.75 hoursRequired cost is 38.
Material is 10 so labour is 28.
At 8 per hours, this is 28/8 = 3.5 hoursAs it is mentioned in the question about the efficiency changes will have no effect on current material cost per unit, why did we not subtract the material cost per unit of $10 during the actual cost calculation?
February 7, 2018 at 4:22 pm #435719Got it. Thanks for the help, John.
February 7, 2018 at 3:21 am #435601Ah, okay. But could you please give me the link of that specific lecture where I would find the explanation about solving that question?
March 2, 2016 at 9:02 am #302985Thanks to you for the help. I got understand the difficulty of this question.
- AuthorPosts
Viewing 4 posts - 1 through 4 (of 4 total)