Forum Replies Created
- AuthorPosts
- April 15, 2019 at 2:20 pm #512869
Affiliate finally, cannot believe, 4th attempt. 62pass mark. Earlier attempts 39 on both occasions!!! I do recommend Kashif Kamran you tube video, I watched couple of times couple earlier sittings, helped a lot on exam technique, more than lsbf lectures a s revision.
October 17, 2016 at 4:07 pm #344350Thank you Open tuition for your great lectures!!! 1st attempt and passed it with 51% Did self study with BPP revision kit and OT lectures:) Now, P6 and P7 left…..
April 18, 2016 at 3:00 pm #311327Passed on my 2nd attempt. Did not expect it at all, but did my best!!! So happy:) Now, P3 in September
October 19, 2015 at 5:25 pm #277591Got it finally!!!!My 4th attempt and 55%. Thought that September exam was really tough, especially 20MCQ. Moving onto P2 now.
May 31, 2015 at 12:19 pm #250942I do apologize, but I couldn’t view my post nowhere. It won’t happen again.
May 30, 2015 at 11:53 am #250512Throughput Q:
Co makes 2 products: X and Y.
X Y
SP 50 32
Material 10 6
Labour 20 15
Assembly time 20min 15min
Max demand 1500 units 1000unitsTotal assembly time is limited to 600hrs. Using throughput, how many units Y should produce?
First contribution:
X: 50-10=40/0.3hrs=133.3, so X FIRST
Y: 32-6=26/0.25hrs=104, Y SECONDX: 1500u*0.3=450hrs
Y: 600u*0.25=150hrsWhere am I getting wrong, as my answer of 600units does not match any of the mock exam?
May 29, 2015 at 9:20 pm #250360Throughput Q:
Co makes 2 products: X and Y.
X Y
SP 50 32
Material 10 6
Labour 20 15
Assembly time 20min 15min
Max demand 1500 units 1000unitsTotal assembly time is limited to 600hrs. Using throughput, how many units Y should produce?
First contribution:
X: 50-10=40/0.3hrs=133.3, so X FIRST
Y: 32-6=26/0.25hrs=104, Y SECONDX: 1500u*0.3=450hrs
Y: 600u*0.25=150hrsWhere am I getting wrong, as my answer of 600units does not match any of the mock exam?
May 27, 2015 at 8:25 pm #249689Good Afternoon. I’ve been trying to calculate Fixed Overhead Efficiency variance.
Budget prod. 13,120u Actual prod. 12920u
Budget fixed o/h $45,920 Actual fixed o/h $48400
Budget labour hrs 26,240 Actual labour hrs 25,200I took Budget labour hours 26240/budget units: 13120u=2hrs
Then took actual prod. 12920u x2hrs=25840hrs.But I do need a standard rate, how do I calculate it, please? or my thinking is not right?
ThanksMay 26, 2015 at 9:33 pm #249341@dreamersk said:
Please can you explain further as I am totally lost as to how question 2 should be answered. The answer in the mock exam is 18 636 units which confuses me even more.Hi. I think, I finally got it:) In order to achieve a profit of £144,000, with a contribution of £10.56 and fixed cost of £52800(which is Product X: 10000unitsx2.88 + Product Y: 12500unitsx2.40, but minus Y specific fixed o/h of £6000) you get Total Contribution of £ 196796, divide by contribution per unit of £10.56 you get 18636 units, when you round it up. I have done the same logic previously, but for some reason couldn’t get the correct answer.
May 24, 2015 at 8:55 pm #248632Please let me know how to calculate the below Q’s:
1. A Co is intending to produce a new product. They have made two test units, the 1st took 8hrs, and the 2nd took 6hrs. What is learning rate?
2. E Co makes 2 products X and Y
SP 24 19.20
Materials 8.40 9.60
Labour 3.60 2.40
Var.O/H 1.44 0.96
Fixed O/H 2.88 2.40Profit per unit 7.68 3.84
Budgeted production: X: 10000 / Y: 12500 units
The Fixed O/H included in X relate to an apportionment of general O/H costs only. However, Y also includes specific fixed cost of $6000. If only X were to be made, how many units would need to be sold in order to achieve a profit of $144000?
May 23, 2015 at 5:43 pm #248208Great lectures, thanks a lot. I went through all of them, and I am a bit confused. In Q5 of the specimen exam paper Labour efficiency operational variance has been calculated as: Actual hrs worked and Rev.Std.hrs for actual production and cost out per Orig. Std Cost of $12. However similar Question in December 2012, cost out per Revised Std. of $11.40. Do we cost out per Original Std. Cost or Revised Std. Cost?
Thank you.
May 30, 2014 at 7:19 pm #171984Thank you. I also noticed when you click Fix, you get a decimal as well. Great! thanks again.:)
February 16, 2014 at 8:33 pm #15902155%, 2nd attempt.
February 13, 2013 at 9:17 pm #117800Passed, 62%, so pleased…
- AuthorPosts