Will optional paper also going yo be cbe from march 2020?
Thank you very much. My problem is solved
from my earlier study i know that initiation means building the business case .
but when i started reading examiner model answer i found under project initiation heading it said establish project initiation document (PID)which include objective ,scope , constraints ,authority
difference between examiner answer and my earlier study makes me so much confuse .
please clear my problem ..
you mention that Conduct = doing the project: broadly planning, execution, control .
but examiner model answer refer conduct as -; two aspect in the conduct of the project deserve scrutiny . the first is procurement process and 2nd is group and stakeholder management .
i cant relate your answer with examiner model answer .
please help me . i need your help
thank in advance.