• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

kalange

Profile picture of kalange
Active 1 month ago
  • Topics: 0
  • Replies: 1
  • ☆
  • Profile
  • Forums
  • Topics Started
  • Replies Created
  • Engagements

Forum Replies Created

Viewing 1 post (of 1 total)
  • Author
    Posts
  • September 16, 2018 at 3:36 am #474720
    be125cce5addff8c1aaf61de5011f1c96d3b36d420874cb00064b5101c006dd1 80kalange
    Participant
    • Topics: 0
    • Replies: 1
    • ☆

    *The highest and lowest activity levels above 5500 units and their associated costs are chosen:

    (1) Variable cost per unit = [(54,800 – 50,000) ÷ (7,500 – 6,000)] = $3.20

    *You can use either activity level (high or low); it will give the same answer:

    (2) Total fixed cost above 5,500 units = [54,800 – (7,500 × 3.20)] = $30,800

    *Because the highest and lowest activity levels were above 5500, we can assume that a step up of 10% has already occurred and that our Total fixed cost of $30,800 is actually 110% in value (i.e. 100% + 10% =110%), so to determine the total fixed cost without the extra 10%, we divide the Total fixed cost of $30,800 by 110% to bring it to a value of 1% (i.e. $30,800 ÷ 110 =$280), we then multiply the 1% value by 100 to bring it to 100% value (i.e. $280 x 100 = $28,000):

    (3) Total fixed cost below 5,500 units = 30,800/110 × 100 = $28,000

    *Now that we’ve determined Total fixed cost at 100%, we can now use it to calculate the total fixed cost at different activity levels:

    (4)Total cost for 5,000 units = [(5,000 × 3.20) + 28,000] = $44,000

    Kaplan text example explanation

  • Author
    Posts
Viewing 1 post (of 1 total)

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Kim Smith on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)
  • Farhaan on Project management – ACCA Strategic Business Leader (SBL)
  • Ken Garrett on Professionalism, ethical codes and the public interest – ACCA Strategic Business Leader (SBL)
  • thienan0110 on Interest rate risk management (1) Part 5 – ACCA (AFM) lectures
  • Venoth on Time Series Analysis – ACCA Management Accounting (MA)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in