• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

Save 20% on ACCA & CIMA Books

Interactive BPP books for June 2026 exams, recommended by OpenTuition.
Get discount code >>

Protected: jasmineleelei

Profile picture of jasmineleelei
Active 2 years ago
  • Profile
  • Forums
  • Topics Started
  • Replies Created
  • Engagements

Forum Replies Created

Viewing 1 post (of 1 total)
  • Author
    Posts
  • March 5, 2019 at 11:57 am #507722
    Avatarjasmineleelei
    Participant

    Sorry, I should reply here:

    Thanks John, so should it be seen as whatever is not saved, then it becomes a relevant cost for new project?

    If under the situation that the labour is in spare capacity, the relevant cost is none. But the labour pay is not saved as well, why it is not a relevant cost? I mean, under both situations (spare capacity and no-spare capicity), the labour pay is not saved in both. This makes me confuse.

  • Author
    Posts
Viewing 1 post (of 1 total)

Primary Sidebar

Donate

Donate

If you have benefited from OpenTuition please donate

Donate now

You can also “donate your time” and help out other students on the Students Forums

BPP

Spread the word

Please spread the word so more students can benefit from our study materials.

Donate

If you have found OpenTuition useful, please donate



Copyright © 2026 · Contact · Advertising · OpenLicense · About · Sitemap · Privacy Policy · Cookie settings · Comments · Log in