hi Sir, help me
MCQ
Michel has the following results.
10,080 hours actually worked and paid costing $8,770
If the rate variance is $706 adverse, the efficiency variance $256 favourable, and 5,000 units
were produced, what is the standard production time per unit?
1.95 hours
2.08 hours
1.96 hours
2.07 hours
Sir please Explain this question.
Vare produces various inks at its Normanton factory. Production details for Process 1 are as follows:
Opening work-in-progress, 1 April 400 units 60% complete
Closing work-in-progress, 30 April 600 units 20% complete
Units started 1,000
Units finished 800
The degree of completion quoted relates to labour and overhead costs. Three-quarters of the materials are added at the start of the process and the remaining quarter added when the process is 50% complete. The company uses the FIFO method of cost allocation.
The equivalent units of production for materials in the period are:
a 680
b 1250
c 850
d 1000