please sir the same question;how did they get this figure’s;8 staff * 1.5hour* 6day*4 week=288extra hour
at $12 per hour =$3456 extra wages
total flexed wage=$9216+$3456=$12672.please sir break it down for meOctober 11, 2012 at 3:49 am #105136thanking sir
October 10, 2012 at 3:21 am #105134please sir how did they get the extra 15 per day
October 4, 2012 at 2:38 am #105132yes is december 2010 q3. i
September 23, 2012 at 3:59 am #76449thanking u said
September 1, 2012 at 3:44 pm #104786is fundamentals pilot paper-skill module question 3,thanks
September 1, 2012 at 1:38 am #104784yes
August 13, 2012 at 11:18 pm #104053thanks
August 8, 2012 at 1:53 am #102365thanking sir