13. The following data are given:
Standard details for one unit:
Direct materials
Direct wages:
Bonding department
Finishing department
40 square metres at $5.30 per square metre
48 hours at $2.50 per hour
30 hours at $1.90 per hour
Budgeted costs and hours per annum:
Variable overhead:
Bonding department
Finishing department
Fixed overhead
Production
Selling and distribution
Administration
Required
i.
ii.
Prepare a standard cost sheet for one unit.
($)
(hours)
375 000
150 000
392 000
196 000
98 000
500 000
300 000
(12 marks)
Calculate the selling price per unit allowing for a profit of 15% of the selling
price.
14.
(3 marks) - AuthorPosts