In Q2 , I got betta something 0.88 or 0.89 do not remember exactly, but surely it was below 1.00 In Q1 there are two different NPVs, but both were acceptable for project Anyone solved like this?
I discounted leasing with 7% , which was given as an interest in “buy” option. There should be a discounting, as it was 10 point question. No discount rate was given for leasing….finding it via IRR I thought it would be not correct, in my opinion, so I discounted with 7 percent