Forum Replies Created
- AuthorPosts
- October 24, 2015 at 4:53 pm #278737
sir where is 10 hours paid?
October 24, 2015 at 4:49 pm #278736A company manufactures a single product L, for which the standard material cost is as follows.
$ per unit
Material 14 kg ? $3 42During July, 800 units of L were manufactured, 12,000 kg of material were purchased for $33,600, of
which 11,500 kg were issued to production.SM Co values all inventory at standard cost.
What are the material price and usage variances for July?
sir I don’t understand. please help meOctober 24, 2015 at 1:43 pm #278720A unit of product L requires 9 active labour hours for completion. The performance standard for product
L allows for ten per cent of total labour time to be idle, due to machine downtime. The standard wage
rate is $9 per hour. What is the standard labour cost per unit of product L?
Sir I am don’t understand this question .October 7, 2015 at 5:45 pm #275444hi,
I am also preparing F2March 7, 2015 at 1:47 pm #231607finished products PS per unit TG per uni
x 12 12
y 6 8
direct materials:
desired closing inventory : X= 6000 kg Y=1000 kg
opening inventory : X=5000 kg Y=5000 kgprepare the material usages budget.
i am unable to calculate. please help me.
January 20, 2015 at 5:16 pm #223105department S T
allocated or apportioned fixed overhead $60,000 $100,000
total cost of direct materials used $120,000 $100,000
total productive labour hours 5000 10,000a particular product ha the following variable cost.
Materials
department S 3 kg @ 4 per kg $12
department T 2 kg @ 4 per kg $8
Labour
department S 1/2 hour @10 per hour $5
department T 1and 1/2 @10 per hour $15
variable overheads 1 hour @5 per hour $5
———————— ———
total 45if fixed overheads are absorbds on the basis of departmental material cost, the fixed overhead cost per unit is:
Sir i am unable to solve that math.Help me sir..
January 20, 2015 at 4:41 pm #223092rent:2000
rates:1000
plant insurance:1000
plant depreciation:10000
supervisor’s salary:7000
———–
total : 21000
department A department B department C
area 3800 3500 700
value of machinery($000) 210 110 80
number of employee 34 16 20the total budgeted monthly fixed overhead cost for department C is:
Sir i am unable to solve that math.Please help me.
January 17, 2015 at 2:59 pm #222879Thank you so much sir.
January 15, 2015 at 5:01 pm #222739A factory consists of two production cost centres (A and B) and two service cost centres (X and Y). The total
allocated and apportioned overhead for each is as follows:
A B X Y
$12,000 $17,000 $9,500 $8,000It has been estimated that each service cost centre does work for other cost centres in the following proportions:
A B X Y
Percentage of service cost centre X to 60 40 – –
Percentage of service cost centre Y to 35 35 30 –
The reapportionment of service cost centre costs to other cost centres fully reflects the above proportions.After the reapportionment of service cost centre costs has been carried out, what is the total over-
head for production cost centre A?sir i am unable to solv this math..
please help meDecember 31, 2014 at 6:03 am #221836Thank you so much 🙂
December 28, 2014 at 4:23 pm #221729Thank you sir 🙂
But answer not matched with BPP text book.December 25, 2014 at 5:00 pm #221620output(unit) total cost($)
26 6566
30 6510
33 6800
44 6985
48 7380
50 7310when output is 80 unit or more, another factory unit must be rented and fixed therefore increase by 100%
variable cost per unit is forecast to rise by 10%in 2014.
calculate the estimated total costs of producing 100 units in 2014.
sir i am able to calculated
VC per unit: $31 per unit
fixed cost: $5760then i am unable to calculate Estimated total cost of producing 100% units in 2004.
Please help me sir.
- AuthorPosts