Standard yield from actual input of materials at standard cost ……….$19552
Actual yield at standard materials cost …………………………………………$20800
Sir, why the difference between them should be favourable? Because actual yield is more than standard, that is why I am thinking it is adverse.
Can you explain it deeply please?