- This topic has 1 reply, 2 voices, and was last updated 3 days ago by .
Viewing 2 posts - 1 through 2 (of 2 total)
Viewing 2 posts - 1 through 2 (of 2 total)
- You must be logged in to reply to this topic.
OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › JIT system
Which of the following is/are necessary for the successful operation of a just-in-time purchasing system?
1. Long-term contracts with suppliers
2. A reliable forecast of the level of demand
3. An effective quality assurance programme
A. 2 only
B. 1 and 3 only
C. 2 and 3 only
D. 1, 2 and 3
The correct answer is D.
Sir, I didnt understand how 2 is correct ?
isnt JIT focused on producing only when the order is made? so why will we need to know what the level of demand would be ?
While JIT is a pull system that aims to produce only when there is an order, having a reliable forecast helps in planning and timing orders to avoid stockouts and production delays.
Thus all three components are integral to the effective functioning of a JIT system.