• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

Bottleneck process (Kaplan 240.2)

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Bottleneck process (Kaplan 240.2)

  • This topic has 3 replies, 2 voices, and was last updated 6 hours ago by LMR1006.
Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • August 16, 2025 at 5:17 pm #718781
    Aynur02
    Participant
    • Topics: 22
    • Replies: 19
    • ☆

    Hello dear tutor, I have a long question. Even though I try every time, I cannot understand the process. Could you please explain it to me in a simple way? I would really appreciate it.

    Sweet Treats Bakery makes three types of cake: brownies, muffins and cupcakes. The costs,
    revenues and demand for each of the three cakes are as follows:
    ………………………………………Brownies …………..Muffins ………….Cupcakes
    Batch size (units) ……………….. 40……………………30…………………..20
    Selling price ($ per unit) ……. 1,5 …………………. 1,4 …………………..2
    Material cost ($ per unit) ….. 0,25 ……………….. 0,15 ………………. 0,25
    Labour cost ($ per unit) ……. 0,40 ……………….. 0,45 ………………. 0,50
    Overheads ($ per unit) …….. 0,15 ………………… 0,20 ………………. 0,30
    Minimum daily demand (units)..30………………..20……………………10
    Maximum daily demand (units)..140………………90…………………..100

    The minimum daily demand is required for a long-term contract with a local café and must
    be met.

    The cakes are made in batches using three sequential processes: weighing, mixing and
    baking. The products must be produced in their batch sizes but are sold as individual units.
    Each batch of cakes requires the following amount of time for each process:
    ………………………………………Brownies ……….Muffins ………….Cupcakes
    Weighing (minutes) ………….. 15…………………15…………………..20
    Mixing (minutes) ……………….. 20……………….. 16…………………..12
    Baking (minutes) ……………… 120……………….. 110………………. 120

    The baking stage of the process is done in three ovens which can each be used for eight hours
    a day, a total of 1,440 available minutes. Ovens have a capacity of one batch per bake,
    regardless of product type.
    Sweet Treats Bakery uses throughput accounting and considers all costs, other than material,
    to be ‘factory costs’ which do not vary with production.

    QUESTION:
    On Wednesday, the mixing process is identified as the bottleneck process. On this day,
    only 120 minutes in the mixing process are available.
    Assuming that Sweet Treats Bakery wants to maximise profit, what is the optimal
    production plan for Wednesday?

    A) 80 brownies, 30 muffins and 100 cupcakes
    B) 0 brownies, 90 muffins and 100 cupcakes
    C) 120 brownies, 0 muffins and 100 cupcakes
    D) 40 brownies, 60 muffins and 100 cupcakes

    August 16, 2025 at 10:15 pm #718785
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1544
    • ☆☆☆☆☆

    Why are you spending so much time on 2 mark questions?

    August 17, 2025 at 8:57 am #718790
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1544
    • ☆☆☆☆☆

    The mixing process is the bottleneck with only 120 minutes available, we need to analyse the throughput of each product and the time required for mixing. Follow a process with throughput:
    1. Batch Sizes & Mixing Time
    2. Throughput Calculation
    3. Throughput per Minute
    4. Ranking by Throughput per Minute
    5. Production Plan
    6. Maximising Remaining Time
    7. Final Optimal Production Plan
    Thus, the optimal production plan for Wednesday
    is A) 80 brownies, 30 muffins, and 100 cupcakes.

    August 17, 2025 at 9:07 am #718792
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1544
    • ☆☆☆☆☆

    Batch Sizes and Mixing Times:
    B take 20 m per b of 40 units
    M 16 m per b 30 u
    C 12 m per b 20 u

    Throughput Calculation:
    B 1.50 – (0.25 + 0.40 + 0.15) = 0.70
    M 1.40 – (0.15 + 0.45 + 0.20) = 0.60
    C 2.00 – (0.25 + 0.50 + 0.30) = 0.95

    Throughput per Minute:
    B 0.70 / 20 = 0.035
    M 0.60 / 16 = 0.0375
    C 0.95 / 12 = 0.0792

    Ranking by Throughput per Minute:
    * C, M, B

    Production Plan:
    To maximise profit, we should first meet the minimum demand:
    1 batch of C (20 units) = 12 minutes
    1 batch of M (30 units) = 16 minutes
    1 batch of B (40 units) = 20 minutes

    This totals 48 minutes, leaving 72 minutes available.

    After fulfilling minimum demand, we can produce more Cupcakes and Muffins:

    Produce 5 batches of C (100 units) = 60 minutes
    Then 1 batch of M (30 units) = 16 minutes
    This totals 76 minutes, which exceeds the available 72 minutes.

    The best combination that fits within the 120 minutes while maximizing profit is:
    80 B (2 batches) = 40 minutes
    30 M (1 batch) = 16 minutes
    100 C (5 batches) = 60 minutes

    Total = 40 + 16 + 60 = 116 minutes.
    Thus, the optimal production plan for Wednesday is A) 80 brownies, 30 muffins, and 100 cupcakes

  • Author
    Posts
Viewing 4 posts - 1 through 4 (of 4 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • ZaidRaza on IAS 16 Accounting for a revaluation – CIMA F1 Financial Reporting
  • mrjonbain on Chapter 11 Capital Gains Tax – Individuals TX-UK FA2023
  • james33 on Chapter 11 Capital Gains Tax – Individuals TX-UK FA2023
  • John Moffat on Group Accounts The Consolidated Income Statement (part b) – ACCA Financial Accounting (FA) lectures
  • John Moffat on Activity Based Costing part 2 – ACCA Performance Management (PM)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in