• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

RE: YAM CO (June 09) (Adapted)

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › RE: YAM CO (June 09) (Adapted)

  • This topic has 4 replies, 2 voices, and was last updated 7 months ago by LMR1006.
Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • November 22, 2024 at 11:26 am #713430
    Shane77
    Participant
    • Topics: 1
    • Replies: 1
    • ☆

    Dear John,

    If Yam Co has decided to purchase a brand new pressing machine thus increasing the available hours on the pressing process to 450,000 hrs (AKA bottleneck shifting- It would result in the inevitable creation of another bottleneck resource.)

    What is the new bottleneck for Yam Co?

    The answer is the Rolling process. But if this is the case, then the data should have stated that it should be processing time (in hours) per unit, not the processing time (in hours) per meter [being indicated by the question] as it might confuse readers to a certain extent.

    May I ask how do I identify the bottleneck resource if the amount of sheet metal utilized by each product is not stipulated clearly? I would gladly appreciate you in helping me to deconstruct this point as to why it is the case. Thanks.

    Regards,
    Shane

    November 22, 2024 at 4:24 pm #713432
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1511
    • ☆☆☆☆☆

    If this question has been modified, it is years old anyway……

    Here’s the video that John did on the original question.
    https://www.youtube.com/watch?v=8Y3aIvgXSHU

    To identify the new bottleneck resource after increasing the available hours for the pressing process to 450,000 hours, you need to analyze the processing times for each product across all processes (pressing, stretching, and rolling).
    With the increased capacity in pressing, you would calculate the production capacity for stretching and rolling to determine which process now has the lowest capacity.

    Regarding the concern about the lack of clarity in the amount of sheet metal utilised by each product, it is essential to understand that the bottleneck is determined by the process that limits overall production capacity.

    Even without specific quantities of sheet metal, the processing times provide sufficient information to identify the bottleneck by comparing the time taken for each process across all products.

    November 22, 2024 at 7:47 pm #713439
    Shane77
    Participant
    • Topics: 1
    • Replies: 1
    • ☆

    Understood. Thanks a lot for helping me to see this through from a different perspective. I’m just wondering if each unit of product A uses 1 meter of sheet metal as the calculation used to determine the pressing time needed for Product A to satisfy maximum demand for 300 000 units is (0.5 * 300 000)= 150 000 pressing hours for Product A whereby this is derived from the multiplication of the time taken per unit, which is 0.5 hrs per meter per unit by the maximum demand of 300000 units for product A.

    (As this is an adapted question, I have difficulty with this part here. I am able to calculate the TPAR from the earlier part of this question.)

    Thanks.

    November 22, 2024 at 9:58 pm #713442
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1511
    • ☆☆☆☆☆

    I hope you don’t mind me saying it is a very old question which you have said has been amended
    By who? BPP?
    Is it actually exam standard?
    You should be looking at newer questions……

    November 22, 2024 at 10:23 pm #713443
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1511
    • ☆☆☆☆☆

    18 hrs* 5 days * 50 weeks * 50 lines = 225.000 hours in total
    225,000 / 0.5 hrs pu = 450,000

    Where is the 300,000 from?
    Metre of material?

    My advice move on from this question

  • Author
    Posts
Viewing 5 posts - 1 through 5 (of 5 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • o1lim on Discounted Cash Flow Further Aspects, Replacement – ACCA Financial Management (FM)
  • julio99 on Impairments – Impairment (CGU) – ACCA Financial Reporting (FR)
  • effy.sithole@gmail.com on EPS – diluted EPS Example – ACCA Financial Reporting (FR)
  • Ken Garrett on The Finance Function in the Digital Age – CIMA E1
  • DeborahProspect on ACCA SBR Specimen Exam 2 Question 1

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in