• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

June 2025 ACCA Exam Results

Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for June 2025 exams.
Get your discount code >>

Please explain this

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Please explain this

  • This topic has 1 reply, 2 voices, and was last updated 1 year ago by LMR1006.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • November 1, 2023 at 2:19 pm #694280
    Shanezehra
    Participant
    • Topics: 1
    • Replies: 0
    • ☆

    MM manufactures three components, S, A and T, using the same machines for each. The budget for the next year calls for the production and assembly of 4,000 of each component. The variable production cost per unit of the final product is as follows:
    Machine hours Variable costs $
    1 unit of S 3 20
    1 unit of A 2 36
    1 unit of T 4 24
    Assembly 20
    Only 24,000 hours of machine time will be available during the year, and a subcontractor has quoted the following unit prices for supplying components: S $29; A $40; T $34.
    Required
    Advise MM.

    November 2, 2023 at 8:27 am #694300
    LMR1006
    Keymaster
    • Topics: 4
    • Replies: 1517
    • ☆☆☆☆☆

    The variable cost of buying in – difference between making it or buying it
    You have got scarce resource
    You can’t make everything
    So you make those which are most expensive to buy in per unit of scarce resource

    S. A. T
    9. 4. 10

    They use

    3. 2. 4. Machine hrs which are in short supply

    So divide one by the other

    3. 2. 2.50

    You make as many of S that you can, then T then A
    Up to a max of 4000 units of each

    S. 4000 units at 3 hrs. = 12000 hrs of the 24000 hrs that are available
    T Only 3000 units at 4 hrs = 12000 hrs so you have used all the hours up

    Then buy in the extra
    T 1000 units
    A 4000 units

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • John Moffat on FA Chapter 6 Questions Depreciation
  • Nkhata@48 on CIMA BA3 The Statement of Financial Position and Income Statement (part c)
  • Ruevimbo on AA Chapter 6 Questions
  • shahdiya@780 on FA Chapter 6 Questions Depreciation
  • John Moffat on Accounting for Management – ACCA Management Accounting (MA)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in