In Kaplan kit there is question like actual hours work=10080 Paid costing=8770 Rate variance =706 adverse Efficiency variance=256 favorable Unit produce=5000 Standard production time per unit=?
Two options that are very closely 2.07 and 2.08 The right answer is 2.08 I did many time and got answer 2.067 round off to 2.07