Q12 is asking what is the date until which you have to perform subsequent events ? But the mock exam giving a wrong answer If I select 18 Mar 20X9.But the question is telling that the audit report date is 18 Mar 20×9.
I don’t why the correct answer is 31 Mar 20X9.
Even though the explanation of the correct answer is telling that subsequent procedures should be done up until the report date which is 18 Mar 20X9.
Thank you for alerting me to the glitch – the correct hot spot is indeed 18 March – I have asked that it be corrected consistent with the answer justification.