• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • CIMA Forums
  • Ask CIMA Tutor
  • FIA
  • OBU
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March and June 2025 exams.
Get your discount code >>

Ques 36 ( DIGUNER) black scholes option pricing model

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › Ques 36 ( DIGUNER) black scholes option pricing model

  • This topic has 1 reply, 2 voices, and was last updated 2 years ago by John Moffat.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • May 29, 2022 at 8:25 am #656771
    live
    Participant
    • Topics: 10
    • Replies: 7
    • ☆

    In DIGUNER’s question (ques 36, Kaplan exam kit sep2021-june2022)

    In part (a) of this ques

    For finding Pa( current price)

    The immediate NPV is given $4m and option to purchase land at an agreed price is give $24m within next 2 years .

    According to me to find Pa , we must discount this $24m to get its value at T0 and then add 4 million to the present value of $24m to get Pa.

    But in book solution they have add (4m+24m) then they have discounted the full amount .

    Thing I can’t understand is why they have discounted this $4m again . As it is already on its present value (T0).

    May 29, 2022 at 3:15 pm #656793
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54655
    • ☆☆☆☆☆

    I do not have the Kaplan Kit (only the BPP Kit), however I do have the examiners own answer 🙂

    The wording of the question was very poor (and this was the previous examiner – not the current examiner).

    The examiner has assumed that by ‘an expected NPV of $4M) it meant that the NPV when the development starts will be $4M and as therefore taken Pa as being $28M (the PV of the future flows once the development starts).

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • hhys on PM Chapter 4 Questions Environmental Management Accounting
  • singhjyoti on Conceptual Framework – ACCA SBR lecture
  • John Moffat on Time Series Analysis – ACCA Management Accounting (MA)
  • azubair on Time Series Analysis – ACCA Management Accounting (MA)
  • Gowri7 on Relevant cash flows for DCF Working capital (examples 2 and 3) – ACCA Financial Management (FM)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in