• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for June 2026 exams.
Get your discount code >>

variance costs

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › variance costs

  • This topic has 1 reply, 2 voices, and was last updated 4 years ago by John Moffat.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • December 24, 2021 at 3:42 pm #644769
    maria2020
    Member
    • Topics: 18
    • Replies: 12
    • ☆

    There are various costs needed to know in the variances.

    Budgeted cost = budgeted hours x standard rate
    Actual cost = actual hours x actual rate

    To calculate standard cost we have to calculate standard rate which is the per unit budgeted cost that is calculated as:
    Standard rate = (budgeted cost / budgeted hours)

    However, standard costs can be calculated in three of the following ways:

    1) Standard cost is calculated with budgeted hours like this:
    standard cost = budgeted hours x standard rate

    2) Standard cost is calculated with actual hours like this:
    standard cost = actual hours x standard rate

    3) Standard cost is calculated with standard hours like this:
    standard cost = standard hours x standard rate

    Is that all correct? Please let me know if there is any mistake because it is really important for me to know.

    December 25, 2021 at 8:21 am #644796
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54835
    • ☆☆☆☆☆

    Yes, that is all correct.

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • The topic ‘variance costs’ is closed to new replies.

Primary Sidebar

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE Exams – Instant Poll

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Aadhi69 on Groups – Other points – ACCA SBR
  • Aadhi69 on Basic group structures – SFP workings and adjustments – ACCA (SBR) lectures
  • Hopemas on MA Chapter 2 Questions Sources of Data
  • John Moffat on The management of receivables – Simple settlement discount – ACCA Financial Management (FM)
  • Jay15 on The management of receivables – Simple settlement discount – ACCA Financial Management (FM)

Copyright © 2026 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in