Transfer priceForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Transfer priceThis topic has 1 reply, 2 voices, and was last updated 3 years ago by John Moffat.Viewing 2 posts - 1 through 2 (of 2 total)AuthorPosts August 22, 2021 at 6:11 am #632467 wroheetParticipantTopics: 8Replies: 1☆past paper Man co ( June 2016)Divison L ( selling division ) capacity of plant is 300,000 ( spare capacity is 140000) external demand is 160,000Divison M ( buying division ) Capacity of plant is 130,000 external demand is 120,000how many units Div L should sell to Div M??120,000 or 130,000??? August 22, 2021 at 9:51 am #632507 John MoffatKeymasterTopics: 57Replies: 54479☆☆☆☆☆120,000 units (as per the examiners answer).Given that Division M only has demand for 120,000 units, they are not going to buy more than 120,000 components from Division L.AuthorPostsViewing 2 posts - 1 through 2 (of 2 total)You must be logged in to reply to this topic.Log In Username: Password: Keep me signed in Log In