• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

December 2025 ACCA Exam Results

Post comments & Instant poll

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March 2026 exams.
Get your discount code >>

BPP REVISION KIT 19/20 Q107

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › BPP REVISION KIT 19/20 Q107

  • This topic has 1 reply, 2 voices, and was last updated 5 years ago by John Moffat.
Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • November 25, 2020 at 1:51 pm #596406
    rihxrau
    Participant
    • Topics: 1
    • Replies: 0
    • ☆

    Can you please explain out the answer to me because it is quite confusing in the answers.

    Q107) A company wishes to go ahead with one of three mutually exclusive projects, but the profit outcome from each project will depend on the strength of sales demand, as follows:

    Strong demand Moderate demand Weak demand
    Profit Profit Profit/(Loss)
    Project 1 70,000 10,000 (7,000)
    Project 2 25,000 12,000 5,000
    Project 3 50,000 20,000 (6,000)

    Probability 0.1 0.4 0.5
    of demand

    What is the value to the company of obtaining this perfect market research information, ignoring the cost of obtaining the information?
    ? $3,000
    ? $5,500
    ? $6,000
    ? $7,500

    107) The correct answer is: $7,500
    EV of Project 1 = (0.1 × 70,000) + (0.4 × 10,000) – (0.5 × 7,000) = $7,500
    EV of Project 2 = (0.1 × 25,000) + (0.4 × 12,000) + (0.5 × 5,000) = $9,800
    EV of Project 3 = (0.1 × 50,000) + (0.4 × 20,000) – (0.5 × 6,000) = $10,000
    (Syllabus area C5(b))
    (Syllabus area C6(b))
    Project 3 would be chosen on the basis of EV without perfect information. With perfect information, this decision would be changed to Project 1 if market research indicates strong demand and Project 2 if market research indicates weak demand.
    EV with perfect information: (0.1 × 70,000) + (0.4 × 20,000) + (0.5 × 5,000) = $17,500
    Value of perfect information = $(17,500 – 10,000) = $7,500 – ignoring the cost of obtaining the informatio

    November 25, 2020 at 6:17 pm #596443
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54812
    • ☆☆☆☆☆

    You will have to say which bit of the answer is confusing you.

    I assume that you have watched my lectures on decision making under uncertainty and therefore understand the idea of expected values and how we calculate the value of perfect information?

  • Author
    Posts
Viewing 2 posts - 1 through 2 (of 2 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Molter on PM Chapter 8 Questions Cost Volume Profit Analysis
  • Payal18 on PM Chapter 8 Questions Cost Volume Profit Analysis
  • arpitJ9803 on The financial management environment – ACCA Financial Management (FM)
  • John Moffat on FA Chapter 8 Questions Irrecoverable Debts and Allowances
  • John Moffat on Activity Based Costing part 1 – ACCA Performance Management (PM)

Copyright © 2026 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in