• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

December 2025 ACCA Exam Results

Post comments & Instant poll

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March 2026 exams.
Get your discount code >>

Relevant cost

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Relevant cost

  • This topic has 3 replies, 2 voices, and was last updated 5 years ago by John Moffat.
Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • August 10, 2020 at 11:10 am #579799
    kennigara
    Participant
    • Topics: 193
    • Replies: 250
    • ☆☆☆

    Hi Dear Tutor, I have a question

    I took this example from Bpp study text “short-term decision” chapter

    Special job will require 20 hours of skilled labour. The skilled workforce is paid $15 per hour and is working at full capacity. If the special job is undertaken, the skilled labour would be taken off the work that earns a contribution of $12 per hour,after deducting the costs of the labour and variable overheads of $1.5 per hour.

    Labour cost of 20 hrs *15$ per hour=300

    Variable overhead costs 20hrs * $1.50 per hour=30

    Contribution forgone (lost contrubution) 20hrs * $12 per hour=240

    total relevant cost======570

    Ennerdale multiple choice question number 108

    Labour

    The contract requires 800 hours of skilled labour. Skilled labour is paid $9.50 per hour. There is a shortage of skilled labour and all the available skilled labour is fully employed in the company in the manufacture of Product P

    Selling price per unit—-100

    Skilled labor cost per unit—-38

    Other variable cost per unit-22

    Contrubution =40

    Labour hout per unit=38/9.50=4 hours per unit

    Skilled labour —800* $9.50 labour cost per hout=7600

    Lost contrubution (40/4=10*800)============8000
    relevant cost ========================15600

    Variable cost per unit=====22

    Direct labour hour per unit==4

    variable cost per hour=22/4=5.5

    variavle cost (800*5.5)-is not considered here? but above example as we can see that

    “Variable overhead costs 20hrs * $1.50 per hour=30”

    f the special job is undertaken, the skilled labour would be taken off the work that earns a contribution of $12 per hour,after deducting the costs of the labour and variable overheads of $1.5 per hour.

    it says contribution after labour and variable cost!

    August 10, 2020 at 3:44 pm #579844
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54812
    • ☆☆☆☆☆

    The second example is more relevant as far as the exam is concerned.

    The reason for the different in the treatment however is that in the first example the variable overheads are being incurred on a labour hour basis and therefore both labour and variable overheads will still be paid if the labour is moved to the new job.

    In the second case the variable overheads are on a per unit basis and so they will not be paid if the labour is moved to the new job.

    August 10, 2020 at 4:40 pm #579857
    kennigara
    Participant
    • Topics: 193
    • Replies: 250
    • ☆☆☆

    Since “direct variable cost per unit” is calculated in the following way based on standard cost card approach then we can break it down into two parts.Standard cost card usually shows per unit approach such as direct material cost per unit , direct labor cost per unit, variable overhead production per unit. At least they should mention it in the question variable cost is hour based or unit based.

    1) variable cost per hour

    2) labor hour per unit

    in the second example labour hour per unit is 4 hours and if I place 4 hours in 2) then I can find variale cost per hour which is 5.5.

    August 11, 2020 at 9:04 am #580082
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54812
    • ☆☆☆☆☆

    The question does mention it!

  • Author
    Posts
Viewing 4 posts - 1 through 4 (of 4 total)
  • The topic ‘Relevant cost’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Sarailee95 on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)
  • John Moffat on PM Chapter 8 Questions Cost Volume Profit Analysis
  • John Moffat on FA Chapter 8 Questions Irrecoverable Debts and Allowances
  • Payal18 on PM Chapter 8 Questions Cost Volume Profit Analysis
  • Sergiu on FA Chapter 8 Questions Irrecoverable Debts and Allowances

Copyright © 2026 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in