past paper march/june 2019 Cara CoForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › past paper march/june 2019 Cara CoThis topic has 3 replies, 2 voices, and was last updated 5 years ago by John Moffat.Viewing 4 posts - 1 through 4 (of 4 total)AuthorPosts August 2, 2020 at 10:15 pm #579010 kennigaraParticipantTopics: 193Replies: 250☆☆☆Does the feasible region include the intersection of Machine hours and demand of Herdorf or does it cover the intersection of both product’s demand point?Thanks in advance August 3, 2020 at 8:56 am #579028 John MoffatKeymasterTopics: 57Replies: 54812☆☆☆☆☆The feasible region is bounded by the H line and the machine hours line. August 3, 2020 at 9:56 am #579039 kennigaraParticipantTopics: 193Replies: 250☆☆☆Thank you very much. August 3, 2020 at 1:25 pm #579060 John MoffatKeymasterTopics: 57Replies: 54812☆☆☆☆☆You are welcome 🙂AuthorPostsViewing 4 posts - 1 through 4 (of 4 total)The topic ‘past paper march/june 2019 Cara Co’ is closed to new replies.