June 2025 ACCA Exam Results

Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for June 2025 exams.
Get your discount code >>

Throughput accounting

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Throughput accounting

  • This topic has 5 replies, 2 voices, and was last updated 5 years ago by John Moffat.
Viewing 6 posts - 1 through 6 (of 6 total)
  • Author
    Posts
  • February 16, 2020 at 1:09 pm #562006
    sarah762
    Member
    • Topics: 67
    • Replies: 127
    • ☆☆

    Hi,

    What does this mean?
    “Work in progress should be VALUED AT MATERIAL COST only until output is eventually sold”

    And also, how does reducing the cost of spare capacity improve throughput accounting ratio? What does spare capacity means?

    February 16, 2020 at 4:39 pm #562020
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54707
    • ☆☆☆☆☆

    When a company makes there own goods, then the cost of the finished goods is the materials used, plus the labour and overheads of making them. Work-in-progress is only part finished and will only have had some of the labour and overhead work done. The statement is saying that it would be valued just at the material costs and none of the labour and overheads should be included.

    Spare capacity is where they are capable of producing more than they are actually producing. Reducing the cost reduces the factory cost per hour which improves the TPAR.

    February 16, 2020 at 6:00 pm #562038
    sarah762
    Member
    • Topics: 67
    • Replies: 127
    • ☆☆

    Thank you!

    Why labour and overheads shouldn’t be included in the work in progress?

    February 17, 2020 at 5:35 am #562066
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54707
    • ☆☆☆☆☆

    Because throughput accounting treats them as being a fixed cost in the short term.

    February 17, 2020 at 10:08 am #562089
    sarah762
    Member
    • Topics: 67
    • Replies: 127
    • ☆☆

    Thanks!

    February 17, 2020 at 1:52 pm #562102
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54707
    • ☆☆☆☆☆

    You are welcome 🙂

  • Author
    Posts
Viewing 6 posts - 1 through 6 (of 6 total)
  • The topic ‘Throughput accounting’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Ken Garrett on Strategy : real life examples – ACCA Strategic Business Leader (SBL)
  • RitikaR29 on Financial management objectives – ACCA Financial Management (FM)
  • Krishadarwin on Strategy : real life examples – ACCA Strategic Business Leader (SBL)
  • mabdullah31 on Conceptual Framework – ACCA SBR lecture
  • MikeLittle on Illegalities – ACCA Corporate and Business Law (LW) (ENG)

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in