- This topic has 1 reply, 2 voices, and was last updated 12 years ago by .
Viewing 2 posts - 1 through 2 (of 2 total)
Viewing 2 posts - 1 through 2 (of 2 total)
- You must be logged in to reply to this topic.
OpenTuition recommends the new interactive BPP books for December 2024 exams.
Get your discount code >>
Forums › ACCA Forums › ACCA AA Audit and Assurance Forums › Test of controls in procurement of inventories and management function?
Im getting a bit stucked here.
What could be the test of controls to test….
– POs generated through a centralised purchasing dept?
– automatic requisition of inventories when a certain level is reached?
Appreciated for any help! Thanks!!
My answer is:
PO’s generated through a centralised purchasing dept.
– confirm that they have been authorised by the appropriate supervisor /manager who actually made the request, to ascertain that it wasn’t a made up order.
-verify that the PO has been authorised by the Purchasing manager, to ascertain that the order has been authorised for purchase.
-Inventories
Test that the Requisition has been approved by the inventory manager, to confirm that the levels were infact at reorder quantity and the inventory dept is requesting more supplies.
—
I hope it helps