ThroughoutForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › ThroughoutThis topic has 1 reply, 2 voices, and was last updated 6 years ago by John Moffat.Viewing 2 posts - 1 through 2 (of 2 total)AuthorPosts August 11, 2019 at 9:20 am #527115 iza1ParticipantTopics: 115Replies: 112☆☆☆Hi JOhn,Can you help me with this TPAR questionA company producing two products has bottleneck resource machine Z that is operated 10 hours a day. Conversion costs for a day is $4600.Product Q : SP – 18 Material cost – 12 Output per hour 80Product P : SP – 15 Material cost – 10 Output per hour 90Now in TPAR calculations , return per factory hour should be throughput / bottleneck hour rightso for Product Q : 6 /10 is this right ? But answer key says 6*80 I cant seem to understand what they have done August 11, 2019 at 10:25 am #527134 John MoffatKeymasterTopics: 57Replies: 54812☆☆☆☆☆The return per hour = throughput per unit / bottleneck hours per unit.If they can produce 80 units per hour, then the hours per unit are 1/80.Therefore the TPAR = 6 / (1/80), which is the same as 6 x 80 = $480.(Or, more logically, if the throughput is $6 per unit and they can make 80 units per hour, then the return per hour = 80 units x $6 = $480.AuthorPostsViewing 2 posts - 1 through 2 (of 2 total)You must be logged in to reply to this topic.Log In Username: Password: Keep me signed in Log In