• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
Free ACCA & CIMA online courses from OpenTuition

Free ACCA & CIMA online courses from OpenTuition

Free Notes, Lectures, Tests and Forums for ACCA and CIMA exams

  • ACCA
  • CIMA
  • FIA
  • OBU
  • Books
  • Forums
  • Ask AI
  • Search
  • Register
  • Login
  • ACCA Forums
  • Ask ACCA Tutor
  • FIA Forums
  • CIMA Forums
  • OBU Forums
  • Qualified Members forum
  • Buy/Sell Books
  • All Forums
  • Latest Topics

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for March 2026 exams.
Get your discount code >>

BOTTLENECK RESOURCES

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › BOTTLENECK RESOURCES

  • This topic has 3 replies, 2 voices, and was last updated 6 years ago by John Moffat.
Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • February 25, 2019 at 8:30 pm #506514
    shalumohta
    Member
    • Topics: 2
    • Replies: 2
    • ☆

    HELLO SIR,
    PLEASE HELP ME WITH THE EXAMPLE COVERED IN TOPIC 5 i. e BOTTLENECK RESOURCE FROM THE NOTES PROVIDED BY OPEN TUITIONS

    February 26, 2019 at 10:33 am #506589
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54814
    • ☆☆☆☆☆

    Please do not type in capital letters.

    You will have to say what your problem is – I assume that you have looked at the printed answer?

    February 26, 2019 at 11:11 am #506595
    shalumohta
    Member
    • Topics: 2
    • Replies: 2
    • ☆

    No sir. only question is given without solution . the question is

    yam co. is involved in the processing of sheet metal into products a,b and c using three processes, pressing, stretching and rolling.
    the factory has 50 production lines each of which contains the three processes: raw material for the sheet metal is first pressed then stretched and rolled. The processing capacity varies for each process and the factory manager has provided the following data:
    Processing time per metre in hours

    product A product B productC
    pressing 0.50 0.50 0.40
    stretching 0.25 0.40 0.25
    rolling 0.40 0.25 0.25
    The factory operates for 2225000 hours
    identify the bottleneck process and explain why this process is described as bottleneck.

    February 27, 2019 at 11:00 am #506681
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54814
    • ☆☆☆☆☆

    The solution is given in the notes. The notes have printed answers to all of the examples.
    Look at the contents page – answers are at the end 🙂

  • Author
    Posts
Viewing 4 posts - 1 through 4 (of 4 total)
  • The topic ‘BOTTLENECK RESOURCES’ is closed to new replies.

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • Kim Smith on What is Assurance? – ACCA Audit and Assurance (AA)
  • LiliyaM on What is Assurance? – ACCA Audit and Assurance (AA)
  • Sarailee95 on IASB Conceptual Framework – Introduction – ACCA Financial Reporting (FR)
  • John Moffat on PM Chapter 8 Questions Cost Volume Profit Analysis
  • John Moffat on FA Chapter 8 Questions Irrecoverable Debts and Allowances

Copyright © 2026 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in